The most common question when kicking off a new development project is:
“How long will it take to get approvals?”
Whether you’re pursuing a site plan approval, development permit, subdivision, or building permit, your project’s success largely depends on how quickly those approvals are obtained.
If you’re buying a site, presenting to investors, or reporting to senior management, everyone wants a timeline.
The problem?
Too many schedules are built on incomplete information.
Someone hears that a similar project received approvals in three months, and that’s enough to build an entire schedule and pro forma around. But very little effort goes into understanding what made that project different.
Was it the same municipality? The same zoning? The same engineering requirements? The same environmental constraints? The same legislation? Did their design include variances?
That three month schedule estimate quickly becomes six.
Six months becomes a year.
Meanwhile, carrying costs increase, financing assumptions begin to break down, market conditions change, and everyone starts asking:
What happened?
In many cases, nothing unexpected actually happened.
The original schedule simply wasn’t based on a complete understanding of the approval process.
Here are three things you (or your development consultant) should do before estimating a permitting timeline.
1. Identify Every Approval You’ll Need
One of the most common mistakes I see is treating “the permit” as though there’s only one approval.
There rarely is just one approval.
Most development projects involve an interconnected series of approvals.
A Development Permit may require reviews from Planning, Engineering, Transportation, Parks, Environmental Services, Building, Fire, Utilities, provincial ministries, regional agencies, or other approval authorities.
Each organization has its own process, priorities, review timelines, and decision-makers.
Even within the same municipality, departments often work independently.
Planning may support your proposal while Engineering requires commitments to significant servicing upgrades before they’ll sign off.
If you don’t identify every approval authority early, you’ll almost certainly underestimate your schedule.
Start by listing every approval your project may require, including approvals from municipal, regional, provincial, and federal agencies where applicable.
Then verify your list with the municipality and also ask your consultants if you’re missing anything.
One of the most valuable questions you can ask is:
“What approvals or agencies am I missing?”
Once you’ve finished this step, you’ll have a complete list of anticipated approvals and permits your project needs.
2. Understand What Each Approval Requires
Approvals don’t simply appear after enough time has passed.
Every permit has submission requirements.
That could include surveys, geotechnical investigations, environmental studies, servicing reports, arborist reports, traffic studies, architectural drawings, or dozens of other technical documents.
Each of those items requires time, consultants and coordination.
For example, something as simple as scheduling a legal survey can be delayed if tenant access needs to be coordinated.
These preparation activities are frequently overlooked when building project schedules.
Take the approval list you created in Step 1 and identify every document or study required for each application.
Ask questions such as:
- What information is required before the application is considered complete?
- Which technical studies are needed?
- Is public consultation required?
- Will Council approval be necessary?
- Are servicing or utility upgrades required before permits can be issued?
Understanding these requirements allows you to estimate not only review times, but also the time needed to prepare a complete application.
3. Map the Approval Sequence
Development approvals rarely happen independently.
Most have prerequisites. There is typically a required sequence.
A Development Permit may be required before a Building Permit.
A Demolition Permit may need to be obtained before subdivision.
An Erosion and Sediment Control Permit may be required before a Soil Movement Permit.
Some applications can proceed in parallel.
Others cannot begin until another approval has been issued.
These sequencing assumptions can dramatically change your project schedule.
That’s why it’s important to ask:
- Which approvals can be submitted simultaneously?
- Which approvals depend on others being completed first?
- Are there opportunities to overlap consultant work or municipal reviews?
Every municipality has slightly different processes in terms of permit sequencing.
Map out all of the approvals and sequence them based on the jurisdiction’s requirements.
This step not only leads to more accurate schedule estimates, but also allows your team to troubleshoot and see where time may be saved.
Summary
Poorly thought out schedule assumptions are costing you money.
Before buying that site and starting that new development:
- Identify every approval you’ll need.
- Understand the requirements for each approval.
- Map the sequence in which they occur.
Will this guarantee faster approvals?
No.
But it will give you a schedule that’s grounded in reality and sets you up for a successful project.
Need Expert Help?
Unexpected permitting requirements are one of the most common reasons development projects experience delays and cost overruns.
At SiteMentor Development Consultants, we help developers and landowners reduce that uncertainty before significant time and money are invested.
Our Development Feasibility Studies identify approval requirements, major project constraints, schedule risks, and key assumptions—giving you a practical roadmap to move your project forward with confidence.