One of the many challenges in real estate development is the rules, costs, and assumptions are constantly changing.
Development fees change.
Interest rates fluctuate.
Construction costs…increase.
Municipal requirements evolve.
Provincial policy shifts.
Sometimes those changes are minor.
And sometimes, those changes are significant enough to materially impact whether a project works, or is no longer viable.
Here is an example of one recent change.
For some projects, particularly larger developments, this could represent substantial savings in development costs.
More generally, it serves as an important land development reminder:
Track your fees closely and regularly revisit your assumptions.
What Are Development Cost Charges?
Development Cost Charges (DCCs) are fees collected by local governments and regional authorities to help fund infrastructure needed to support a growing population.
In British Columbia, DCCs commonly help pay for:
- roads,
- water systems,
- sewer infrastructure,
- drainage,
- and parks.
While the terminology changes depending on what jurisdiction you’re in (ex. Development Cost Charges – DCCs, Development Charges – DCs, Development Cost Levies – DCLs etc.), the concept is generally the same: growth-related infrastructure has costs attached to it.
DCCs are typically paid at Building Permit issuance, or Subdivision approval.
For developers, these fees can become a major component of overall project costs.
And importantly, they do not stay static.
Many municipalities and regional authorities review and update these fee structures annually or periodically, sometimes resulting in significant increases within a short timeframe.
1. Fee Changes Can Be Material
I’ve heard some say that DCCs (and similar fees) are inconsequential due to the fact they are a much smaller percentage of overall project costs compared to construction costs.
I get that…but development viability is often a game of margins.
Even when development fees are not the single largest project cost, they still directly affect:
- lender comfort,
- contingency flexibility,
- and investor returns.
A project that barely “worked” before a fee increase, may no longer be viable after.
Likewise, a reduction or delay in fee increases may materially improve feasibility just enough to make the project go ahead.
This is why the best developers constantly revisit their pro formas.
The numbers are never truly static.
2. “In-Stream” Protection – Valuable…But It Expires
Let’s briefly talk about “in-stream” protection of development fees.
First off, what is it?
Under provisions within British Columbia’s Local Government Act, projects already in the approvals process may receive temporary protection from certain development fee increases.
What does this mean?
It means, if you made a precursor application, such as a development permit submission, and the City or region increased DCCs after you applied, you may be protected from those increases, even though your project hasn’t been fully approved. (Remember DCCs are paid at BP or Subdivision approval).
This protection can be extremely valuable.
But it is not permanent.
The protection window eventually expires (typically one year after the increase was made by the municipality), and projects that do not advance to BP issuance within the required timeframe can become subject to newer, and often higher, fee structures.
I have seen developers miss this expiry despite their best efforts simply because approvals took longer than expected. I have also seen situations where development teams were not aware the protection timeline had run out. Don’t be that team.
The lesson is simple:
Track your timelines carefully, understand when fee protections expire, and continually reassess the financial implications if approvals extend longer than anticipated.
3. Development Fees Will Likely Continue Increasing
While the recent Metro Vancouver DCC rollback may provide temporary relief for some projects, the broader long-term trend is likely upward pressure on development-related fees.
Municipalities and regional governments face many of the same inflationary pressures developers do:
- construction costs increase,
- labour costs rise,
- infrastructure becomes more expensive to deliver,
- and servicing demands continue growing.
Concrete, pipes, pumps, roads, and utility infrastructure cost significantly more today than they did several years ago.
There are increasingly active conversations around sharing infrastructure costs more broadly through provincial and federal funding support. However, municipalities still need to fund and deliver major infrastructure systems to accommodate growth.
As a result, developers should expect continued evolution, and likely continued increases, in development-related charges over time.
This is part of the reality of modern development.
Could Your Project Benefit From Expert Guidance?
If you’d like confidence before moving forward, SiteMentor Development Consultants provide industry-best development feasibility reports that identify what your property can realistically support, highlights potential constraints, and helps you determine the development strategy that makes the most sense for your goals.